| Existing | 2,700 kW IT load, 3N/2 (UPS #1 + #2). Utility 20,641 kW from five feeds. Generation 15,600 kW from nine units (4 × 1.25, 2 × 1.8, 2 × 2.25, 1 × 2.5 MW). Cooling 2,491 tons N+1, air-cooled via CRAH: 8,760 kW of IT cooling. |
| Phase I · Q1 2027 | Ready for service March 31, 2027. 4,050 kW IT load (+1,350 kW), 3N/2. New UPS #3: 3 × 750 kW with 3-string BESS; roof PMH9 and MSDA transfer to an alternate feed. No utility, generator or mechanical scope; the existing plant carries Phase I. |
| Phase II · Q3 2027 | Ready for service September 30, 2027. 9,250 kW IT load (+5,200 kW), 4N/3. New UPS #4–#8 and a new 4,000 A distribution board. Utility 23,216 kW: sixth feed adds 2,575 kW at Winston. Generation 27,600 kW: four new 3 MW units with paralleling gear. Cooling 4,128 tons N+1: four Trane Ascend chillers on new redundant 12-inch loops add 65°F in-row liquid cooling, for 14,517 kW of IT cooling. |
| Phase III · Q2 2028 | Ready for service April 30, 2028. 19,000 kW IT load (+9,750 kW), 4N/3. Nine new 1,250 kW UPS with 5-string BESS and new switchgear. Utility 37,216 kW: seventh feed adds 14,000 kW at Buxton (24 kV) under a Duke Energy letter agreement, with service on or about April 30, 2028. Generation 39,600 kW: four more 3 MW units with additional paralleling gear. Cooling 6,856 tons N+1: five more Trane Ascend chillers (nine total) and additional chilled-water loops, for 24,111 kW of IT cooling. Long-lead procurement orders are not yet placed. |
| Note | Capacities are cumulative. Phase dates are planning estimates, subject to change, and not a commitment to any delivery or service-commencement date. Source: WEC Phased Capacity Diagram, October 22, 2026 (PDF). |